Timeline

Month 1 - Month 5

  • Asbestos Containing Material Removal✔
  • Building Material, Ecology, Air Emission and Noise Survey✔
  • CMC Power Plant Trees Removal to Coloane Power Plant✔
  • CMC Fuel Removal and Transfer to Coloane Power Plant(D15-D21;T22/T23) ✔
  • CMC HFO Tanks Cleaning Prior Demolition✔
  • Equipment Dismantling and Removal (D-15-D21; T22/T23)✔

 Month 5 – Month 13

  • Equipment Dismantling and Removal (D25-D28)✔
  • CMC Stack Demolition Works
  • Demolition of D25-D28 Engine Hall
  • Demolition of Power Plant Control Building✔
  • Demolition of D15-D21 Engine Hall✔

Month 13 – Month 18

  • Completion of the Works
  • Site Demobilization
  • Macau Power Plant Land Handover to Macau SAR