Decomissioning, Decontamination and Demolition (DDD) of Macau Power Station

Timeline

Month 1 - Month 5

  • Asbestos Containing Material Removal
  • Building Material, Ecology, Air Emission and Noise Survey
  • CMC Power Plant Trees Removal to Coloane Power Plant
  • Equipment Dismantling and Removal
  • CMC Fuel Removal and Transfer to Coloane Power Plant
  • CMC HFO Tanks Cleaning Prior Demolition

 

Month 5 – Month 13

  • Start Demolition (Mega Structure and Buildings Structure)

 

Month 13 – Month 18

  • Completion of the Works
  • Site Demobilization
  • CMC Power Plant Land Handover to Macau SAR.