- SCOPE OF SUPPLY-SERVICES
- VARIATION ORDERS

|
The word "Changes" as used hereafter, means
substitutions, additions, deletion, modifica-tions in
this scope of the Contract.
|
 |
Changes shall be administered according to the following
procedure:
- CEM issues instructions to Contractor, on his own
behalf or upon suggestions made by the Contractor to
carry out changes.
- The Contractor submits a proposal, a cost estimate
and the impact on the time schedule for completion.
- CEM issues a Variation Order.
- In case of urgency - in the event that an urgent decision
is required with regards to changes to be carried out
and in order not to disrupt the Works, verbal instructions
may be given but shall be confirmed in writing as soon
as feasible
|
- SUBLETTING

|
The Contractor shall not Contract with any sub-Contractor
or any vendor who is to supply equip-ment, materials,
service, or to perform Works at site without prior written
consent of CEM. The Contractor shall be responsible for
all acts, defau-lts, neglects of his subcontractor, and
for the observance by these sub-contractors of the terms
and con-ditions of this Contract.
|
 |
CEM shall not be responsible for delays and costs incurred
by the Contractor because of disapproval of a sub-contractor
or vendor or the late submittal of his name for approval.
|
- ASSURED QUALITY
The Contractor warrants that upon delivery, all materials and
equipment will be new, free from material and structural defects
and the most suitable for the services required, as per CEM specifications
Back to top

- CONTRACTOR REPRESENTATIVE
Before commencing the Works the Contractor shall appoint a competent,
English-speaking Project Manager to represent and act for the
Contractor during the execution of the Works. The authority of
the Project Manager shall be clearly defined and the scope of
this authority with any possible limitation shall be submitted
to CEM.
- TIME SCHEDULE WORK CHART

|
The Contractor shall submit to CEM's approval a detailed
time schedule.
|
 |
All the Works shall be performed in accor-dance with
this time schedule.
|
 |
After approval by CEM this time schedule shall become
an integral part of the Con-tract Document. The time schedule
cannot be altered except if the alteration is approved in
writing by CEM. |
- TECHNICAL DOCUMENTS

|
The Contractor, if applicable, shall submit to CEM's
approval the drawings, specifications, etc. request-ed
in the Technical Documents, in accor-dance with the contractual
Time Schedule.
|
 |
All the documentation drawings sent by CEM to the Contrac-tor
remain CEM's property and shall not be reproduced and/or
disclosed to any third party without CEM's written consent.
|

- PACKING - MARKING
The Contract Price shall be deemed to include the cost of proper
packing and protection in accordance with international practices.
The Contractor shall mark any parts of any delivery so as to assure
a clear identification of the contents.
- TRANSPORTATION - HANDLING
The Contractor shall be responsible for the shipment and handling
up to the site of installation of all materials to be supplied
under this Contract at his cost and risk. The Contractor shall
inform CEM at least 2 working days in advance of any delivery.
- DELIVERY
All materials shall be delivered to the address men-tioned in
the special conditions.
- TRANSFER OF TITLE AND RISKS
All equipment and material supplied under this Contract shall
become the property of CEM upon signature of the Taking Over Certificate.
The risks for the Works shall pass to CEM upon the same date.
- LIQUIDATED DAMAGES
If the Contractor fails to complete the Works and hand over of
the same in accordance with the Speci-fications at the specified
time for completion, a liquidated damage shall apply as defined
in the Special Condi-tions of Contract.
Back to top

- GENERAL RESPONSIBILITIES

|
The Contractor shall provide all labour including the
supervision thereof, all other things and services to
perform the Works in accordance with the Contract and
within the specified time.
|
 |
The Contractor must anticipate in his schedules that
the performance of the Works may interfere with the concurrent
activity of CEM. The Contractor shall cooperate with CEM
to avoid any delay or hindrance which may be caused by
this activity. No exten-sion of time for completion shall
be grant-ed and no extra payment be made to the Contractor
as a result of such temporary interferences, except if
otherwise agreed upon. The Works shall be proceed strictly
according to the instructions as stated in the Technical
Specifications.
|
- SAFETY AND SECURITY RULES
- EXTENSION OF TIME FOR COMPLETION

|
If by reason of changes instructed in writing by CEM
or any cause beyond the control of the Contractor, the
Contractor shall have been delayed/impeded in the execution
of the Works he shall request in writing an extension
of time for completion of the Works. An exten-sion of
time which CEM considered reasonable may be granted in
writing without thereby prejudicing the validity of the
Contract.
|
 |
The Contractor shall have no other claim against CEM
in respect of delays arising from the occurrences hereabove
mentioned provided that the scope of Works has not been
changed.
|