Contractor means the person(s), firm, company, consortium,
joint venture, whose Tender has been accepted by CEM and includes
the Contractor's personnel, successors and permitted assignees.
Time for completion means the guaranteed time of completion
of the Works as defined hereinafter.
Site(s) means all places where the Works are to be executed
or other places provided by CEM for the purposes of the Contract.
Contract Price means the sum finally agreed upon subject
to such additions hereto or deductions therefrom as may be made
under the provisions hereinafter contained.
LOA letter of acceptance means letter notifying the selected
Tenderer of the acceptance by CEM of his Tender and setting out
the Contract conditions.

- This Contract shall enter into force upon the signature of
the Letter of Acceptance, not with standing the provisions set
forth in the Instruc-tions to Tenderers whereby, the Contractor
shall arrange to commence the Works upon receipt of the Letter
of Acceptance. It shall cease upon signature of the Defects Liability
Certificate.
- This Contract shall consist of the following documents including
their amendments and other related documents:
* The Letter of Acceptance
* The Special Conditions of Contract
* These General Conditions of Contract
* The Tender Specification
* The Minutes of Clarification meetings (if applicable)
* The Tenderer's Proposal
- Each Contract document shall constitute an integral part of
this Contract to the extent that each shall interpret and complement
the other.
- In case of apparent contradictions in the Contract documents,
to the extent that they cannot be reconciled, the preceding document
shall prevail over the documents that follow, in the sequence
set forth here above and, for documents on the same level as per
above list, that document issued at a later date shall prevail
over the earlier ones.
- The Contractor, by accepting the LOA waives his general and
any particular terms and/or conditions of Business, except as
otherwise agreed upon.
- Except as otherwise provided for, no certificate given, no payment
made nor any approval shall be construed as acceptance of faulty
or defective works nor as relieving the Contractor of his obligation
under this Contract to provide all the means necessary for a proper
and professional execution of the Works.
- If the Contractor intends to supply equipment which deviates
from the description given in the Tender, it shall obtain prior
written approval from CEM.
Back to top

- The Contractor hereby declares that:

|
he possesses the necessary professional qualifications,
skilled personnel, expertise.
|
 |
he will make available the necessary facilities, manpower
and services to perform the Works in an efficient, workmanlike
and timely manner in accordance with all the conditions
and terms of this Contract. |
- CEM hereby agrees to pay the Contractor in consideration of
the execution of the Works the Contract prices at the times and
in the manner prescribed by the Contract.
Back to top

Nothing contained in this Contract or any sub-Contract awarded
by the Contractor or any agreement between the Contractor and
any third party shall create any Contractual relationship between
CEM and any third party, except as otherwise agreed upon.
Back to top

- The Contractor shall be deemed upon signature of this Contract
as having investigated and satisfied himself concerning the general
and local conditions in Macau and particularly, but without limitation,
with respect of the following:
and all other matters which can in anyway affect the performance
of the Works or the cost associated with it.
- Failure of the Contractor to acquaint himself with any applicable
conditions will not relieve him from his responsibility to properly
estimating the difficulties or the cost of performing the Works
at CEM's satisfaction.
Back to top

The Contractor shall be deemed to have satisfied himself as to
the correctness and sufficiency of the prices which shall cover
all his obligations under this Contract and all matters, and things
necessary for the proper execution of the Works.
Back to top

- The Contractor shall guarantee the due fulfillment of its obligations
under this Contract by providing at his own expense a Performance
Security in the form described below.
- The Performance Security shall remain in force until 30 days
after the date of Taking Over insofar as the Contractor has by
that date fulfilled his obligations.
- The Performance Security shall preferably be in the form of
an unconditional bank Security or a certified cheque, in an amount
of 10% of the Contract price.
Bank security shall be payable in Macau and shall be issued by
one of the approved banks. It must be payable to CEM on first
demand, without any need for judicial settlement and despite any
objection by the Contractor or the bank.
Certified cheque shall be payable to CEM in Macau and drawn on
one of the approved banks in Macau.
- Due authority for an extension of the validity of this Performance
Security shall be lodged by the Contractor with the Bank of Guarantor
concerned if such extension is desired by CEM.
- Should the Contractor fail to produce evidence of the establishment
of the Performance Security on time, CEM shall be entitled to:

|
seize the Tender Security (if applicable);
|
 |
terminate the Contract without compensation for the Contractor. |
Before applying such measure, CEM will send the Contractor a registered
letter giving formal notice regarding the establishment of the
Performance Security. This notice shall set a new time limit which
will take effect from the date of postage of the letter.
- Should the Contract price be changed by means of Variation
Orders, the Contractor shall adjust the security accordingly.
Should the Contractor fail to do so, CEM may deduct such equal
amount from future payments and use it to replenish the Performance
Security.
|