CEM

Contact us Customer advocate Sitemap






1972 – 1989


As a result of this study, in 1972 a new concession company was formed – Companhia de Electricidade de Macau – CEM, S.A.R.L. (CEM), an incorporated company with a capital stock of MOP20 million with the following shareholders: Sociedade de Turismo e Diversões de Macau (STDM) (MOP6 million), Macau

Signature of CEM Constitution

Government (MOP6 million), Leal Senado (around MOP2 million), BNU (around MOP2 million) and Macau Canidrome Company, Sociedade de Pelota Basca and Sociedade Won Ho (each with MOP1 million).

 

Silencers and exhausts for engines number 9, 10, 11, 12 and 14

There was no doubt that the arrival of CEM was eagerly awaited. The public were fed up with MELCO and warmly welcomed the new concessionaire company supporting it unconditionally even in the beginning when the first problems arose. The public was convinced that CEM needed some time to solve the pre-existing electricity problems.

However, the revolution of 25th April 1974 in Portugal, and its consequences for Macau (further aggravated by the oil crisis), which among other things included the change of the Governor of Macau, impeded the reconstruction plans of CEM. For instance, the construction of the power station in Coloane was one of the biggest projects at that time. It was delayed to a point that the Japanese companies involved in the project had to be compensated. In addition, customers protested against the increase in tariffs, and many of them did not pay their bills for several months. As a result of this, the corresponding debt rose to several MOP million.

CEM and electricity began to be known in the Portuguese press as the “number one problem in Macau”. The financial and technical situation of CEM continued to deteriorate, and even the conclusion of the construction of the new Coloane Power Station could not solve the problems CEM faced.

In August 1979, Melo Egídio decided that the production and supply of electricity granted to CEM would be directly provided by the Government.

In July 1981, the Macau governorship changed again, and Commander Vasco de Almeida e Costa arrived in the Territory to take office. In February 1982, the new members of the Administrative Committee of CEM, engineers Amilcar Martins, Rui Neves and Tavares Pires and economist Carlos Reis took charge. The first item on the agenda of the new management team of CEM was to make a survey of the situation in the company. Two months later, CEM submitted a memorandum to the Government denouncing the existence as a “deteriorating situation”. The new managers pointed out the fact that the existing generators in the Macau Power Station, which had been installed between 1959 and 1971, showed high consumption and high maintenance costs. The biggest problem was the difficulty in finding spare parts in the marketplace.

 

CEM Building

As for the network, the report mentions that distortion existed because the electricity of Macau was supplied from only one extreme location of the peninsula (the same place where Marius Bert and Ricou had installed the first power station 70 years previously). As a result of this, bigger investments in cables to counter high losses in the network were needed. The tariff system, according to the managers, did not show any correspondence with the cost structure of CEM.

Based on this report, Almeida e Costa in June 1982 made a long presentation to the Legislative Assembly, mainly concerning CEM. Considering the severity of the situation, the Governor declared the mobilization of “the energy and the means to resolve the situation”.

While tackling the big problems facing the company, the new management team took measures to resolve the smaller problems as well. For instance, they conducted a campaign against theft of electricity and also targeting late payments. They began by putting up posters on the streets and thereafter used radio announcements in an effort to create awareness among the people. Penalties were applied without hesitation to defaulters. Finally, a truce was announced and a period of one month was given to all customers to settle their bills. In this stated period, there were long queues of people waiting to settle their bills, and around 80% of the customers had regularized their accounts. The message had been understood and in one-and-a-half months MOP30 million from late payments had been collected.

In November 1983, Almeida e Costa presented a new proposal to the Legislative Assembly, in which he defended the changing of CEM into a company of mixed capital, and in June of the following year a contract was signed between the Territory, CEM and STDM, with the objective of turning CEM into a viable company. In the same month Almeida e Costa approved the reduction of 6.5% in electricity tariffs and a decree was published marking the end of Government intervention in CEM. At the same time, the company shareholders during an extraordinary General Assembly elected a new management board. Finally, two years later, the connection with the electricity network of Guangdong province was completed.

The results appeared very quickly. In 1984, for the first time in the history of the company, CEM showed profits and the report of the Board of Directors, stated “(financially speaking) CEM is now in a position to face its responsibilities.”

The following years confirmed the success of CEM. Nobody believed that the “cancer” of the Territory (another expression for “CEM”), which had absorbed significant resources of the state treasury, had turned itself around. The viability of CEM had finally become a reality. Therefore, the most recent years of CEM’s history are filled with objectives that were aimed more at growth and modernization rather that just resolution of problems, as had been done in the past. From 1st January 1987, a system of pensions for the workers of the concessionaire was instituted; this represented a big innovation among private companies in Macau.

Coloane - A Power Station (CCA).

In May, Group 3 of the Coloane-A Power Station (CCA) commenced operations with a potential of 24 MW. It was the first unit of a new technology of slow Diesel groups of high reliability and high output. According to those responsible at CEM, “this option was extremely positive for the future of the company, because the benefits from increased productivity in production had permitted stabilization of the tariffs”. The following years, new slow Diesel groups were installed successively: Group 4 of 24 MW in 1988, Groups 5 and 6 each of 37.5 MW in 1991 and 1992 respectively, and another two of 53 MW, in 1995 and 1996 respectively.

In 1987, the basic network of the substations was completed, with the commencement of the functioning of S. Paulo and D. Maria substations. By the end of the year, the company had shifted its daily operations to the new CEM building next to the Macau Power Station, situated in Estrada D. Maria II.

Symbolically, CEM returned to its origins, transferring its headquarters to the place where everything started around 80 years ago, where it began producing electricity for the first time to the city of Macau.

For the first time in CEM’s history, the results of 1987 activities permitted the payment of dividends, thus attracting new shareholders.


Back to top

 

Copyright © 2003 Companhia de Electricidade de Macau - CEM, S.A. All rights reserved. ESTRADA D. MARIA II, MACAU